Launching of M-beam

Location: Bridge pier 17 to 16, NBCT
Date: 04/06-09, Thursday
Time: 8.30 a.m - 7.00 p.m
No. of beam: 18
Length: 24.475 m
Weight: +/- 21 tan
Manufacturer: Associated Concrete Products (ACP), Gurun's Plant
Machines Used: Mobile crane KATO 200 tan


Beam yg cukup pjg, dok jauh pon x cukup frame kamera lagi


Mai dari Gurun, Kedah mende ni


Close up M-beam. Nampak cam M ke??


Yg hitam tu namanya bearing pad


Memastikan bearing pad pada kedudukan yg btoi


Kren 200tan digunakan utk mengangkat beam


Proses meletakkan beam


Project Manager tgh memberikan arahan


Saat2 beam ke-18 nak diletakkan pada 6.56p.m.


Beam yg dah siap dipasang

  • Digg
  • Del.icio.us
  • StumbleUpon
  • Reddit
  • Twitter
  • RSS

2 Response to "Launching of M-beam"

  1. AnneAnne says:
    June 10, 2009 at 4:12 PM

    Najib, i did lost your url before. ish baru start bace balik. btw, sgt suke sbb banyak entry!!!
    yana dah follow blog najib so lepas ni each time najib update blog yana tahu. yeayy~
    :D

  2. bijan87 says:
    June 10, 2009 at 10:37 PM

    tenkiu, tenkiu, thanks for the support
    najib akan try perbaiki lagi blog ni nanti, insyaallah

Post a Comment